SIPC

Project Name

Coal Ash Pond Retrofit

Client

SIPC

Location

Marion, IL

SIPC contracted O6 ENV to provide project management, field resources, labor, and equipment to remove impacted soil removal at their Power Plant in Marion, IL.

O6 ENV utilized heavy equipment to remove over 15,000 cubic yards of contaminated material from an existing coal ash pond. This material was staged onsite for dewatering and T&D at a later date.

O6 ENV transported over 15,000 cubic yards of clay material from an onsite borrow source to bring the pond back to the design grades. The pond was compacted in lifts to 95%.

O6 ENV subcontracted GSI to install the 60mil HDPE geomembrane. 6 pipe penetrations were needed to keep drainage on their site functional. An anchor trench was dug and backfilled around the perimeter to keep the liner in place. No material was placed on the liner since they will be using this pond for rainwater events.

Latest News

Industrial waste characterization drums facility

Hazardous Waste

Industrial Waste Characterization: A Facility Guide

Industrial facilities generate a wide range of waste materials through manufacturing, maintenance, equipment cleaning, and ...

Read Article
Industrial chemical storage spill prevention equipment

Emergency Response

Industrial Spill Prevention: A Facility Guide

Industrial spills can disrupt operations, damage equipment, and create risks for employees, surrounding properties, and ...

Read Article

Tell Us Your Challenge. We’re Here to Assist.

"*" indicates required fields

Name
Subscribe to our email newsletter