SIPC

Project Name

Coal Ash Pond Retrofit

Client

SIPC

Location

Marion, IL

SIPC contracted O6 ENV to provide project management, field resources, labor, and equipment to remove impacted soil removal at their Power Plant in Marion, IL.

O6 ENV utilized heavy equipment to remove over 15,000 cubic yards of contaminated material from an existing coal ash pond. This material was staged onsite for dewatering and T&D at a later date.

O6 ENV transported over 15,000 cubic yards of clay material from an onsite borrow source to bring the pond back to the design grades. The pond was compacted in lifts to 95%.

O6 ENV subcontracted GSI to install the 60mil HDPE geomembrane. 6 pipe penetrations were needed to keep drainage on their site functional. An anchor trench was dug and backfilled around the perimeter to keep the liner in place. No material was placed on the liner since they will be using this pond for rainwater events.

Latest News

Press Releases

O6 Environmental Announces Strategic Expansion with New Facility in Tyler, Texas

O6 Environmental Expands Service Reach with New Tyler, Texas Location, Elevating Industrial and Environmental Solutions ...

Read Article
cleanup press conference

Press Releases

City taking next step toward transforming former Rhodia site into a community-led mixed-use development

Photo Credit: LouvilleKy.gov “In 2022, Metro Council approved the allocation of $10 million in federal ...

Read Article